Famagusta District: Development projects of 45 million euros starting in 2022

Major development projects amounting to 45 million euros will begin to be implemented within 2022. According to the official planning of the Government provided by the Famagusta.News, the major development projects that are starting to be implemented within this year, concern, among other things, improvements of existing infrastructure, creation of road networks, configuration of central squares as well as creation of a new Fire Station in Ayia Napa.

The biggest infrastructure project that starts to be implemented within 2022 is the improvement of the Deryneia - Sotiras road, the cost of which is expected to exceed 15 million euros, as the asbestos water pipeline will be replaced with a corresponding metal one.

More specifically, the utility projects that will start to be implemented in 2022 are worth more than 18 million euros, while Paralimni and Ayia Napa will see the start of implementation of development projects that exceed 12 million euros in 2022.

Detailed table with the development projects that start within 2022:

FAMAGUSTA - PUBLIC BENEFIT (Total: € 18.400.000)

  • Improving the reliability of the drinking water supply system (project "Kokkinokremmos") for Paralimni, Ayia Napa, Deryneia and Sotira, to meet water needs - PHASE 2.
    • Date of Announcement: 25/2/2022
    • Start Date: 25/11/2022
    • Completion Date: 25/3/2024
    • Contracting Authority: Ministry of Agriculture, Rural Development and Environment
    • Cost: € 2.500.00
  • Enrichment of two artificial reefs in Paralimni and Ayia Napa.
    • Date of Announcement: 23/12/2021
    • Start Date: 23/3/2022
    • Completion Date: 23/3/2023
    • Contracting Authority: Ministry of Transport, Communications and Works
    • Cost: € 300.000
  • Improvement of the Sotiras - Deryneia road and replacement of the asbestos water pipeline with a corresponding metal one.
    • Date of Announcement: 16/5/2021
    • Start Date: 16/3/2022
    • Completion Date: 16/10/2024
    • Contracting Authority: Ministry of Transport, Communications and Works
    • Cost: € 15.600.000

Ayia Napa (Total: € 12.687.000)

  • Reconstruction of the coastal front and creation of a coastal pedestrian street in Ayia Napa - PHASE A, PART 2, in the Municipality of Ayia Napa
    • Date of Announcement: 16/3/2022
    • Start Date: 16/7/2022
    • Completion Date: 16/1/2024
    • Contracting Authority: Municipality of Ayia Napa
    • Cost: € 2.200.00
  • Construction of Ayia Napa Fire Station.
    • Date of Announcement: 1/3/2022
    • Start Date: 1/9/2022
    • Completion Date: 1/9/2024
    • Cost: € 3.000.00
  • Creation of a multifunctional park in the Municipality of Ayia Napa
    • Date of Announcement: 16/12/2021
    • Start Date: 16/2/2022
    • Completion Date: 16/6/2023
    • Contracting Authority: Municipality of Ayia Napa
    • Cost: € 3.487.00
  • Accessibility project in the center of Ayia Napa, with the upgrade of "Agia Mavri", "Yuri Gagarin", "Theodosi Pieridi", "Katalimaton", "Grigori Afxentiou", "Ippokratous", "Louka Louka", "25th" streets March "," Xylouri "," Aris Velouchioti "and" Vassilis Michailidis ".
    • Date of Announcement: 1/12/2021
    • Start Date: 1/4/2022
    • Completion Date: 1/4/2023
    • Contracting Authority: Municipality of Ayia Napa
    • Cost: € 4.000.000

PARALIMNI (Total: € 12.700.000)

  • Creation of parking spaces in the Municipality of Paralimni.
    • Date of Announcement: 16/1/2022
    • Start Date: 16/6/2022
    • Completion Date: 16/6/2023
    • Contracting Authority: Municipality of Paralimni
    • Cost: € 7.700.000
  • Formation of the central square of Paralimni - PHASE AD.
    • Date of Announcement: 16/5/2022
    • Start Date: 16/9/2022
    • Completion Date: 16/5/2024
    • Contracting Authority: Municipality of Paralimni
    • Cost: € 5.000.000

BRAKER (Total: € 1.200.000)

  • Core regeneration in Frenaros.
    • Date of Announcement: 16/5/2022
    • Start Date: 16/9/2022
    • Completion Date: 16/12/2023
    • Contracting Authority: Ministry of Interior
    • Cost: € 1.200.000

* It is pointed out that the launch of the projects or the start date may change, while the list of the Government does not include other sub-projects that have been decided to be implemented by the local authorities or cancellations / freezing of projects following decisions of the local authorities.

Famagusta.News

News stream

At 680 euros, the hunger limit for a family of four in the occupied territories

The limit of hunger for a family of four in the occupied territories is from April 30,…

May 8, 2024

Greater interest in apartments compared to houses

Apartments gather more buying interest compared to houses according to the conclusions...

May 8, 2024

Larnaca: In custody three persons who tried to destroy a house with explosives

The District Court of Larnaca today issued a seven-day detention order against three persons aged 32,…

May 8, 2024

They are wanted by the Police for assault and possession of a weapon (PICTURES)

The Police are asking for information to locate TSAMPRATZE GKIORGKI, 18, and NIKOLOZI KOBIAZVILI, 30…

May 8, 2024

Holgin hopes leaders will 'listen to citizens' - Tatar repeats himself

The hope that the leaders of the two communities in Cyprus will be able to "listen to the...

May 8, 2024

SOTIRA: The Children's Club presents the fairy tale "The Matchbox"

This Sunday, May 12, the Children's Reading Club of the Sotiras Municipal Library hosts the...

May 8, 2024