The Municipality of Paralimni - Deryneia informs that the Public Works Department has begun the work of resurfacing roads of primary importance in the Municipal District of Paralimni, which are part of the regular maintenance of the main roads of the Municipality. The work, which constitutes an important intervention for the improvement of road safety and traffic quality, will last approximately two weeks.
The works will be carried out exclusively during the evening hours, with the aim of reducing traffic congestion and avoiding any inconvenience for the residents and visitors of the Municipality. The contractor of the project is the CYBARCO / PHARMAKAS ASPHALT LIMITED Consortium.
Specifically, the work schedule has been determined as follows:
From November 25, 2025 to December 1, 2025: Protaras Avenue (Paralimni), from the intersection with Agios Georgios Street to Papetta Fruit Market, 1.300 m long (E306).
From December 2, 2025 to December 9, 2025: Paralimni Avenue - Sotiras, from the Bank of Cyprus traffic lights to the EKO gas station in Sotira, 2 km long (E304).
The Municipality of Paralimni - Deryneia calls on the public to demonstrate the necessary understanding and comply with the relevant markings during the execution of the works, which aim to improve the safety and functionality of the road network.