The Municipality of Paralimni - Deryneia informs that the Department of Public Works, within the framework of Periodic Maintenance of the Road Network for roads of primary importance, will proceed with road resurfacing works in the Municipal District of Paralimni from Tuesday 25/11/2025 between the hours of 20:00-05:30. The works will last approximately one week and will be carried out during the evening hours to reduce traffic congestion and avoid inconvenience to the Municipalities.
Contractor: CYBARCO / PHARMAKAS ASPHALT LIMITED Consortium
Specifically, the work will be carried out on the following dates and at the following points:
– From November 25, 2025 to December 1, 2025: Protaras Avenue (Paralimni) (From the intersection with Agios Georgios Street to Frutaria Papetta 1.300m. (E306)
– From December 2, 2025 to December 9, 2025: Paralimni Avenue – Sotiras (from the height of the Bank of Cyprus traffic lights to the EKO gas station in Sotira) 2km