Despite the intense heat, the construction works for the Ayia Napa Marina continued in July.
According to the company, significant work has been completed in terms of residential infrastructure. Specifically, the 135 supports that will support the East Tower have been laid, laying the foundations for the superstructure that will follow. The work has progressed considerably in the maintenance, administration and storage buildings.
With the completion of the dredging and the embankment very close to completion, the works for the artificial island have started and are continuing at an intensive pace. The wall of the island is at 44%, making it visible and shaping day by day.
The progress of laying the prefabricated concrete "four-legged" for the creation of the breakwater reached about 73% of the completion of production, accelerating the construction of the southern breakwater.
See below pictures and videos from the progress of the construction works: