Famagusta District: Stagnant projects over 11 million euros (Table)

Important development projects of free Famagusta were "stuck" in bureaucratic procedures

Screenshot 2020 08 16 08 exclusive, Development Projects

In bureaucratic procedures, it seems that important development projects are stuck, which are expected to be promoted in free Famagusta. Overall, according to what it presents today Famagusta.News, the stagnant projects constitute 6,17% of the projects that have been completed or are being implemented in the area and specifically 5 of the 81, while there are projects which, although they are expected to start their operation, are in fact in a state of stagnation with the most important the Deryneia-Sotiras road but also the Sewage Treatment Plant and consequently the Sewerage System of Kokkinochorion, as well as the local plan of the area, which although not included in the development projects that are part of the Government's program, is undoubtedly important element for the future urban and socio-economic development of the whole region.

According to official government figures provided by Famagusta.News, of the 81 projects included in the development program for the province of Famagusta, 44 have been completed (54,32%) at a cost of € 56.193.427, 19 have been launched for implementation (23,46%) at a cost of € 112.938.214, and 13 are under construction (16,05%) at a cost of € 18.060.000

Stationary works

Of the stagnant projects, three are of public benefit for the whole province, one belongs to the Municipality of Paralimni and one to the Municipality of Ayia Napa. Nevertheless, it is clarified that although according to the data of the Government the two projects in Ayia Napa and Paralimni are considered as "stationary", nevertheless the date of their start is part of 2021. According to the official data of the Government who secured the Famagusta.News, the projects are as follows:

  • AYIA NAPA
    • Reconstruction of the coastal front and creation of a coastal pedestrian street in Ayia Napa, in the Municipality of Ayia Napa - PHASE B '
    • Date of announcement: 27/3/2021
    • Start date: 1/6/2021
    • Date of completion: 1/12/2022
    • Contracting Authority: Municipality of Ayia Napa
    • Cost: € 3.000.000
  • PARALIMNI
    • Formation of the central square of Paralimni - PHASE AD.
    • Date of announcement: 19/6/2021
    • Start date: 19/12/2021
    • Date of completion: 19/12/2023
    • Contracting Authority: Municipality of Paralimni
    • Cost: € 5.000.000
  • PROVINCE OF FAMAGUSTA - PUBLIC BENEFIT
    • Improving the reliability of the drinking water supply system (project "Kokkinokremmos") for Paralimni, Ayia Napa, Deryneia and Sotira, to meet water needs - PHASE 2.
    • Date of announcement: 19/3/2021
    • Start date: 19/7/2021
    • Date of completion: 19/7/2022
    • Contracting authority: Ministry of Agriculture, Rural Development and Environment
    • Cost: € 2.500.000
  • PROVINCE OF FAMAGUSTA - PUBLIC BENEFIT
    • Creation of 20 beds of Surgery Clinic on the 2nd floor of the General Hospital of Famagusta.
    • Date of announcement: -
    • Start date: -
    • Completion date: -
    • Cost: € 700.000
  • PROVINCE OF FAMAGUSTA - PUBLIC BENEFIT
    • Relocation of the Famagusta District Administration from Larnaca to the Municipality of Paralimni
    • Date of announcement: -
    • Start date: -
    • Completion date: -
    • Contracting authority: Famagusta District Administration
    • Cost: -