Impressive images from the construction works of the marina

ANMWP2 2019 05 074 Development Projects, Ayia Napa Marina

The construction works of the emblematic project of the Ayia Napa Marina are constantly evolving, a project that promotes the development and highlights the dynamics of the Cypriot entrepreneurship and whose completion will contribute to the promotion of the high tourist profile of Cyprus.

The first phase of the project, which concerns the infrastructure and mooring projects, is nearing completion. In particular, the geotechnical works around the project and the marina basin - earthworks and dredging - have been fully completed, while the works on the southern breakwater, one kilometer, are progressing rapidly, with the installation of the remaining prefabricated concrete units in .

Timelapse Photo Final Design June 2019 Development Projects, Ayia Napa Marina

Advances in geotechnical work and the breakwater have allowed construction teams to proceed with the project road network and the construction of key buildings, such as the government building and the marina management building, which are also included in the first phase, is visible. Progress has also been made on the boat maintenance building, which will play a key role in the operation of the marina.

ANMWP2 2019 04 069 Development Projects, Ayia Napa Marina

As for the projects of the second phase that concern the residential and commercial constructions, they are proceeding normally, with the commercial area of ​​restaurants and shops being visible. The concrete wall around the project has been extended to the platforms that will support the Event Center and the Yacht Club, shaping the structure in the center of the marina.

roundhead Development Projects, Ayia Napa Marina

At the same time, the foundations have been laid for the East Tower that will allow the beginning of its construction. The subsoil and the piles have been strictly inspected and the construction team has carried out the same inspections for the West Tower, the foundation of which will begin soon.

ANMWP2 2019 04 075 Development Projects, Ayia Napa Marina

As stated by the CEO of MM Makronisos Marina Ltd, Mr. Stavros Karamontanis, referring to the progress of this magnificent project: "The completion schedule of the Ayia Napa Marina is strictly followed and soon the project will be an important pole of attraction and promotion of maritime tourism in the Eastern Mediterranean. 85% of the East Tower has already been sold. Ayia Napa Marina, with its operation, will upgrade Cyprus as a destination of quality tourism throughout the year, while today this magnificent project is the largest foreign investment in Cyprus, with international reputation and interest from buyers and investors from different countries ”.

2019 05 09 11.22.14 Development Projects, Ayia Napa Marina

The marina of Ayia Napa

Located between the beaches of Agia Thekla and Makronisos, the Marina of Ayia Napa provides for the construction of 190 spacious, luxurious apartments in two impressive towers, 29 luxury mansions, a marina with the capacity to moor and provide a complete selection of services in 600 boats shops and restaurants that will offer high quality services and amenities to the residents and visitors of Marina.